Construction Updates

Adelphia Gateway pipeline construction is now underway. The project has received all notices and approvals to proceed and is moving forward to bring needed natural gas resources to the Greater Philadelphia Area.

With the growing demand for natural gas in the Greater Philadelphia area, Adelphia Gateway will provide consumers in southeastern Pennsylvania with additional access to an affordable and reliable source of energy.

Check back here for construction updates in your area.

Public and Traffic Updates

Week of May 23, 2022

Cleanup and restoration are nearing completion at most sites. Remaining areas with active construction activities are listed below.

Quakertown Compressor Station (West Rockhill Township): Work continues on the stormwater system and the installation of safety bollards throughout the facility at the compressor station in preparation for precommissioning activities of the compressor units. 

Marcus Hook Compressor Station (Lower Chichester Township) is largely complete. Crews completed the test plan for the piping with nitrogen and will continue installation of the extension on the valves. 

Transco Meter Station (Aston Township): A small crane is on-site to move meters.

 

 

Week of May 9, 2022

Cleanup and restoration continue to be nearing completion at most sites. Remaining areas with active construction activities are listed below.

Quakertown Compressor Station (West Rockhill Township): Crews continue the installation of vent piping and supports at the compressor station. They began installation of the vent piping on Unit 1 and continued backfilling and compacting around the yard piping and compressor building. Electricians continue fabricating and installing the last of the outside lights, as well as testing, tagging and terminating the outside light feeds and fire detectors, and they are installing the egress light wiring. Crews continue supporting commissioning activities.

Marcus Hook Compressor Station (Lower Chichester Township) is largely complete. Awaiting approval of test plan for the nitrogen test for completed piping. 

Transco Meter Station (Aston Township): Currently working with Williams on material acceptance. Crews will be on-site until resolved.

Week of May 2, 2022

Cleanup and restoration continue to be nearing completion at most sites. Remaining areas with active construction activities are listed below.

Quakertown Compressor Station (West Rockhill Township): Crews continue to fabricate the 2-inch piping for the new valve. They began installation of the vent piping on Unit 1 and continued backfilling and compacting around the yard piping and compressor building. Electricians continued pulling, testing, tagging and terminating the wires. H&M testing crews completed a successful hydrotest on the low-pressure fuel gas and low-pressure DPP piping. 

Marcus Hook Compressor Station (Lower Chichester Township) is largely complete. Commissioning support will continue.